Note 6. Research and Development Costs

 

INL Project

 

In 2022, Lightbridge entered into agreements with BEA, to support the development of Lightbridge Fuel™. These framework agreements use an innovative structure that consists of an “umbrella” SPPA and an “umbrella” CRADA, with an initial duration of seven years. Throughout the duration of these umbrella agreements, all research and development (R&D) work contracted with BEA is through the issuance of PTSs. The initial phase of work under the two agreements will culminate in irradiation testing in the Advanced Test Reactor (ATR) of fuel samples using enriched uranium supplied by the DOE. The initial phase of work aims to generate irradiation performance data for Lightbridge’s delta-phase uranium-zirconium alloy relating to various thermophysical properties. The data, which will be obtained during post-irradiation examination work, will support fuel performance modeling and regulatory licensing efforts for the commercial deployment of Lightbridge Fuel™. For the three months ended March 31, 2024 and 2023, the Company recorded $0.4 million and $0.2 million in R&D expenses associated with INL, respectively.

 

Romania Feasibility Study

 

On October 16, 2023, the Company engaged RATEN ICN in Romania to perform an engineering study to assess the compatibility and suitability of Lightbridge Fuel™ for use in CANDU reactors. The total price of approximately $0.2 million is payable in three installments, including an advance payment of $0.1 million and an interim milestone payment and final payment totaling approximately $0.1 million. For the three months ended March 31, 2024, the Company recorded $0.1 million in R&D expenses associated with RATEN ICN.

Centrus Energy FEED Study

 

On December 5, 2023, the Company entered into an agreement with Centrus Energy to conduct a FEED study to add a dedicated LPFFF at the American Centrifuge Plant in Piketon, Ohio. As of the date hereof, Centrus Energy has completed the initial phase of the FEED study and issued a preliminary report. For the three months ended March 31, 2024, the Company recorded $0.2 million in R&D expenses associated with this FEED study. After reviewing the preliminary report, the Company will decide whether to proceed to the final phase of the FEED study. If the Company decides to move forward with the final phase of the FEED study, the remaining work is expected to be completed in 2024 at an additional fixed price cost of approximately $0.3 million.  

 

The following table presents the total R&D expenses for the three months ended March 31, 2024 and 2023 (rounded to millions):

 

 

 

 

March 31,  

 

 

 

2024

 

 

2023

 

INL Project

 

$ 0.4

 

 

$ 0.2

 

Romania Feasibility Study

 

 

0.1

 

 

 

 

Centrus Energy FEED Study

 

 

0.2

 

 

 

 

Allocated employee compensation and stock-based compensation expenses

 

 

0.2

 

 

 

0.1

 

Other outside R&D expenses

 

 

0.1

 

 

 

0.1

 

Total

 

$ 1.0

 

 